Google paused its Belgian AI data center after Belgian authorities ordered work to stop on the 3-hectare site in southern Belgium. The order came after officials said the modified permit had not been approved. The building was nearly finished, so the halt hits a project that was already far along.
Raphaël Stokis on the site
Raphaël Stokis said inspectors found the structure almost complete, with the structural work done, and that 300 workers had been told to stop. He told RTBF: “Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused”.
Google’s 2025 permit fight
The 2025 application changed the plan from air-cooling to water-cooling, and the regional administration approved those amendments in April before residents and protest groups appealed. François Desquesnes revoked the modified permit in August over drought concerns, and Google appealed to Belgium’s Council of State, which is expected to rule on 7 January.
Greenpeace and prosecutors
Google said it had halted works consistent with local authorities’ direction and pending additional guidance, and a company spokesperson said it had operated in Belgium for over 15 years and remained committed to local laws and “an open, collaborative dialogue with government officials and all relevant authorities about our work in Wallonia.” Greenpeace said its drone footage showed Google continuing construction despite the permit revocation, while Nicolas Yernaux said a report was being submitted to public prosecutors alleging “a major offence: the illegal construction of a building covering 3 hectares”.
What decides the next phase is the legal ruling, because that will set whether the modified permit survives or the stoppage continues under the old 2024 permit terms.