As the artificial intelligence (AI) boom transforms America’s energy landscape, data center projects are expanding rapidly. By mid-October, the United States had a data center pipeline totaling 245 gigawatts (GW) of planned capacity. This surge is attributed to several large-scale, speculative initiatives, with a significant concentration in Texas.

The Texas Data Center Boom

Texas leads the charge, with over 25% of the national pipeline capacity designated for the state. Capacity in Texas nearly doubled from 35 GW in Q1 to 67 GW in Q3 this year.

Shifts in Data Center Strategies

Traditionally, data center developers focused on fiber proximity. However, the current emphasis has shifted dramatically towards securing reliable power sources from utilities. This change is evident in the expansive giga-scale campuses proposed in states such as Pennsylvania, Wyoming, and particularly Texas.

  • Pennsylvania
  • Wyoming
  • Texas (West and North)

Developers now seek to harness local natural resources for power generation. A notable focus is on natural gas, particularly from the Permian Basin in Texas.

Examples of Major Projects

  • Pacifico Energy’s 5-GW GW Ranch
  • Poolside’s 2-GW Project Horizon
  • FO Permian’s 5-GW campus in Midland County

While many campuses aim to utilize gas, others leverage solar or wind resources, such as Tract’s data center parks in Nevada and Utah, or Quantica’s Big Sky Digital Infrastructure campus in Montana.

Implications for Capital and Investment

The emergence of mega campuses significantly alters the capital landscape. Projects exceeding $17 billion account for 42% of total capital investment, despite representing only 2% of total projects. In contrast, 60% of projects under $1 billion make up only 8% of overall expenditure.

Notably, the highest-cost projects include:

  • Project Jupiter in New Mexico ($160 billion)
  • Project Kestrel in Missouri ($100 billion)

These projects are financed through innovative approaches like industrial revenue bonds (IRBs), which provide tax advantages. This financial structure allows developers to serve as both issuer and recipient of the bonds.

The Move Towards Onsite Generation

Data center developers have increasingly embraced onsite generation, a shift from previous preferences for grid power. While concerns over operating risks and sustainability persist, the growing urgency among hyperscalers may drive this change.

Currently, 10% of projects in the pipeline incorporate onsite generation, yet they account for 34% of total capacity, primarily using gas turbines and located in Texas.

Future Challenges

This trend could affect energy affordability and reliability across the nation. Projects reliant on utility-scale gas generation will increase demand for natural gas, potentially leading to rising costs for consumers.

As demand for onsite turbines grows, utilities may encounter difficulties in sourcing these essential components, which could challenge their capacity to adequately meet load growth and electrification efforts.

Regardless of the potential volatility in market conditions, these developments may prompt state interventions aimed at consumer protection, fundamentally altering the dynamic of the emerging energy landscape.