Matthews Arena Deconstruction Unveiled: Key Steps and Strategies

Matthews Arena, a historic structure located on the Northeastern University campus in Boston, is set for deconstruction. The arena, which spans 106,000 square feet and can hold nearly 5,000 attendees, has been a significant site since its opening 115 years ago. It will be dismantled to pave the way for a new multi-purpose athletics and recreation complex.

Deconstruction Timeline and Process

The deconstruction process will commence this winter. Suffolk Construction has been appointed to oversee this careful dismantling. Beginning in February, crews will use a high-reach excavator to methodically deconstruct the arena piece by piece, ensuring safety and preservation of materials.

Key Dates:

  • December 13: Final game at Matthews Arena
  • December 15 – January 5: Salvaging of memorabilia by CollectU
  • February: Official start of deconstruction
  • April: Expected completion of the demolition

Salvaging Historic Elements

Before demolition, valuable items such as seating and the basketball court floor will be salvaged. Northeastern University plans to reuse some components in the new facility, including lighting and parts of the scoreboard. Notably, the historic arch built in 1910 will be preserved for integration into the new complex.

Memorabilia Sales

Memorabilia, including seats and bricks from the arena, will be available for sale. These unique pieces will be collected, stored, and sold over the next three years until the new arena is completed.

Preserving Community Safety

Given its location near public transit and community buildings, safety during deconstruction is a priority. Suffolk has developed a comprehensive safety plan in collaboration with local officials and engineers to minimize disruption. A construction fence will secure the site, and police will monitor public access.

Environmental Considerations

Suffolk aims to recycle as much material as possible. Structural steel, bricks, and concrete will be sent to recycling facilities. The concrete will be crushed and repurposed for future construction needs, reflecting a commitment to sustainability.

Future Complex Overview

The new multi-purpose athletics and recreation center will span 310,000 square feet. It is designed to accommodate 4,050 fans for hockey and 5,300 for basketball. The completion is targeted for fall 2028, marking a significant advancement in facilities for Northeastern University.

This deconstruction and subsequent construction reflect both a respect for history and a commitment to modern athletic facilities. As the Matthews Arena is carefully dismantled, its legacy will transition into a state-of-the-art complex that supports future generations of students and athletes at Northeastern University.